Case study showing how Dr. Sauer & Partners used Abaqus FEA for 3D modeling of complex sprayed concrete lined tunnels at Bond Street Station Upgrade.
Dr. Sauer & Partners performed 3D numerical analyses for the Bond Street Station Upgrade on the London Underground using Abaqus/CAE and finite element analysis. The project involved 450 meters of new SCL tunnels near existing structures with strict settlement criteria. Engineers modeled soil-structure interaction across three separate meshes ranging from 450,000 to one million elements to evaluate ground movement, stress on adjacent assets, and optimize tunnel lining design.
3D FEA models provided realistic estimates of ground movement and volume loss during SCL tunneling
Analyses evaluated stress induced in existing structures from new tunnel excavation sequences
Models supported dimensioning of new tunnels and calculation of reinforcement at stress concentrations
Dividing the project into three overlapping models improved computational efficiency for large geometries
Abaqus enabled rapid geometry modifications and high-fidelity simulation of plastic behavior in complex meshes